Step by Step Pool Building
This pool was 10 weeks total to build

Demolition Day - May 24

Starting Excavation - May 25

Excavation - May 25

Excavation - May 25

Excavation - May 25

Rebar Installation - May 28

Rebar Installation - May 28

Plumbing Installation - May 28

Plumbing Installation - May 28

Plumbing Installation - May 28

Plumbing Installation - May 28

Gunite Day - June 24

Gunite Day - June 24

Gunite Day - June 24

Gunite Day - June 24

Gunite Day - June 24

Gunite Day - June 24

Rock Sculpting Day - July 2

Rock Sculpting Day - July 2

Rock Sculpting Day - July 2

Rock Painting Day - July 15

Rock Painting Day - July 15

Masons Start - July 15

Masonry Continues - July 15

Masonry Continues(coping poured) - July 17

Masonry Continues - July 17

Masonry Continues (tile installed) - July 23

Masonry Continues (decking) - July 23

Masonry Continues (decking) - July 23

Masonry Continues (decking) - July 23

Masonry Continues (decking) - July 23

Pebbletec installed - August 2

Pebbletec installed - August 2

Pebbletec Acid Washed - August 3

Pool Filled - August 4

Pool - August 5

Waterfall Running - August 7

 

Home | About | Pricing | Gallery | Step by Step Images | Cost Structure | Why Us? | Contact Us

Copyright 2005-2006 SplashPoolsnSpas all rights reserved

Site design by TonysDesigns.com an AR WebSolutions, Inc. company